Boundary Lane
The Boundary Lane redevelopment project involved converting a former plant nursery site with large, dilapidated glasshouses. These structures contained asbestos cement linings, which posed significant health and safety risks.
Need more info or advice? Speak to an expert
To handle these risks, a detailed demolition plan was created with input from both the demolition contractor and an asbestos removal specialist. This plan focused on safely removing asbestos and managing risks to workers and site visitors.
Key tasks included preparing the Pre-Construction Information Pack, reviewing the Principal Contractor’s Construction Phase Plan, and issuing the F10 Notification to the Health and Safety Executive (HSE). Ongoing design monitoring was also conducted throughout the construction phase to ensure compliance with safety standards. The final Health and Safety file will be completed at the end of the project.